Electricity Company Commissions Geo-Thermal Power Plant


Kenya’s energy firm, Kenya Electricity Generating Company (KenGen) has commissioned a 35 megawatt (MW) third unit at the Olkaria II power plant in Naivasha, about 90 km southwest of the capital Nairobi.

It was co-financed by European investment Bank (EIB) which put in 40.8 million U.S. dollars, the International development Association (IDA) with 27. 6 million dollars and the Agence Francaise de Development (AFD) which provided 20 million dollars with KenGen providing the rest of funds.

The new unit was completed in record 27 months as per schedule and went to commercial operation on May 12.

With the additional power, the Olkaria II power station, the largest geothermal plant in Africa, has a combined output of 105 MW.

KenGen is adding green energy capacity mainly through geothermal energy, which is environment friendly and has no carbon emissions. (Coast Week, June 25-July1, 2010)